Objective:
The objective of this project was to identify and evaluate suitable grounding methods for adhesively mounted equipment that would not damage the paint in completed compartments. Based upon test results and the need for surface preparation, recommendations were made for a number of different grounding methods suitable for late-stage grounding applications.
Request Final Report from NSRP – Limited Distribution authorized to U.S. shipyards and NSRP ASE Program representatives
Overview

Planning, Production Processes & Facilities
Project Team:
- Ingalls Shipbuilding
- AeroNav Laboratories
2016
NSRP ASE Investment: $143K