Overview
Ship Production Rigging Planning Guide (2005-333-R4)
Project Team:
- General Dynamics NASSCO
- General Dynamics Bath Iron Works
- Noran Engineering
2008
NSRP ASE Investment: $100K
Objective:
This project conducted a review of domestic regulatory requirements and standards for rigging within and outside the shipbuilding industry and supported the development of a domestic ship production rigging planning guide. The goal is to provide some of the necessary material to create a knowledgeable rigging engineering workforce. The main guidance produced was in three parts: Lift Check Sheet, Approach Lift Guidance, and Rigging Lift Common Component Catalog.
Key Deliverables:
Final Report – Approved for public release; distribution is unlimited